Understanding the Case:
The case centered around a public institution governed by U.P Avas Evam Vikas Adhiniyam, 1973, facing a complaint concerning the delayed possession of a flat. The institution argued that legislative changes beyond its control were responsible for the delays. However, the aggrieved flat allottee cited delayed possession and various deficiencies, such as absent windows and parking issues.
The Adjudicating Authority acknowledged the delay and directed the institution to compensate the complainant by paying interest for the period of delayed possession. Despite an appeal to the Appellate Tribunal, which collectively rejected multiple appeals, the institution persisted in challenging this decision.
Key Court Observations:
1. Non-Override of Contractual Terms: The Allahabad High Court made a decisive statement, asserting that contractual terms cannot override the retrospective applicability of the RERA. This underscores the court's commitment to ensuring that contractual agreements do not become tools for promoters to evade their RERA-mandated responsibilities.
2. Promoters' Unavoidable Responsibilities: The court emphasized that promoters cannot shirk their responsibilities and liabilities under the RERA, even in cases where delays are attributed to legislative changes. This reaffirms the principle that promoters are accountable for ensuring timely possession and addressing project deficiencies.
3. Preserving Homebuyers' Rights: Citing the precedent set in the case of M/s Newtech Promoters and Developers Pvt. Ltd. vs. State of U.P, the court highlighted that homebuyers retain the right to claim compensation for delays, extending this right even after executing conveyance deeds and taking possession of the property.
Implications for the Real Estate Sector:
This court ruling holds profound implications for the real estate industry. The judgment solidifies the regulatory framework established by the RERA, sending a clear message that promoters must honor their commitments and obligations. Attempting to circumvent responsibilities through contractual terms is not a viable strategy, as the court firmly supports the rights of homebuyers to timely possession and compensation for project delays.
In an evolving real estate landscape, this judgment underscores the importance of transparency and timely project delivery. Promoters must prioritize fulfilling their obligations to maintain the credibility and trust of homebuyers, fostering a healthier and more accountable real estate sector. As the legal landscape evolves, this ruling sets a precedent for the industry, emphasizing the non-negotiable nature of regulatory compliance and promoter accountability.
To Read The Complete Judgment : Click Here